Crew is on site, safety is clean, productivity holding at 92%. A 45-min pipe delivery slip puts schedule 88% on plan (6 days behind). Cost is $120k under.
Schedule
6 days behind plan
88%
on plan
Total delays this week65 min
Wed: 45 min · Mon: 8 min · Fri: 12 min
Cost
$1.23M spent of $3.00M contract
$120k
under plan
$1.23M actual$1.35M planned$3.00M total
Productivity
Crew share of plan, day by day
92%
holding steady
9 days without a safety incident.